Crews are clearing the Giofyros and Agia Irini watercourses in Heraklion in preparation for heavy winter rainfall. Nea Kriti reported that the Drakouliaris is next.

Where the work is focused

Heraklion deputy regional governor Nikos Syrigonakis said the €1 million, three-year contract covers locations where vegetation and debris obstruct water flow. Near the wastewater treatment plant the Giofyros riverbed narrows from roughly 12 metres to four, creating a potential bottleneck during heavy rain.

Cretalive separately reported machinery working on the Giofyros on 6 November and cited the regional authority’s update on Gournes, Gouves and parts of the municipality of Phaistos. Both reports described ongoing work.

What remains to be done

Effective maintenance will require further clearance at narrow points and the removal of debris after severe weather. Residents should follow Civil Protection announcements when warnings are issued.

The image was created with artificial intelligence and is indicative. It does not reflect a specific point or actual workshop of the project.