Temporary traffic arrangements are being implemented from today, Thursday, November 5th, at Bakogianni Street in Heraklion, due to work on the construction of a new water pipeline.

According to the official announcement of the Organization for Development of Crete, the interventions are part of the project to expand the aqueduct from the Aposelemis Dam to the D1 and D3 reservoirs of Heraklion. This section provides for the construction of a 400 mm diameter pipeline.

What changes from today?

The approved worksite signage will remain valid until the work in this section is completed. The notice does not specify the expiry date of the arrangements nor any specific alternative routes.

The construction is undertaken by the Domiki Kritis S.A., while supervision is carried out by the Organization for Development of Crete. The OAK asks drivers and pedestrians to follow the signs and instructions in the area, as excavation work will be carried out.

The image is an AI illustration. It does not depict Bakogianni Street or the actual construction site.